Client:                                    Mercury Engineering

Status:                                   Project completed

The project was delivered on schedule and within budget.

Project Description:          Double Contained Process Drains

Contract Location:             Cruiserath Rd, Blanchardstown, Dublin 15

Contract Duration:             5 Months

Overview:                            

The project involved the manufacture and installation of stainless steel double contained process drains with sizes ranging from ½” to 16”. The internals were manufactured from 316L with the external pipework manufactured from 304L. The finished pipework was serviwrapped prior to delivery to site. All fabrication was done in our workshop in Kilmallock Co. Limerick and installed on site by our site installation team.

25,000 Direct labour hours between workshop and site

Manhole Inside Manhole External Isometric Double contained drains